Trial holes will be dug on on Sunday 10th February, between 0900 and 1800, although the road will not be closed, traffic lights will be used to control traffic so expect some short delays.
Following this the actual work will start on the 4th March 2013 and will run through to the 31st May 2013. During this period part of Back Lane will be closed overnight.
(but see update below)
Map showing extent of Yorkshire Water roadworks |
Yorkshire Water have written to residents to say that the roadworks on Back Lane will run for approximately 10 days from the 4 March 2013. The work will be undertaken overnight and Back Lane will be closed from 6pm to 6am. Diversions will be put in place and access will be maintained for High Hutton residents only.
All material © Philip Stone 2013
Philip
ReplyDeleteAre you sure the roadworks are planned to last until the 31st of May?
Jem
Thanks Jem,
DeleteAt the original site meeting this was the period quoted by Balfour Beattie as their technical man said "Best case is six weeks work". However they've since written to residents to say the road will be closed for about 10 days, I imagine new figure is a result of their test drilling. I've amended the post.
Philip